Day #36 – 2/9/2014

Lab opening 1:20 PM

A good part of the day was spent welding the intake frames and side funnel H frames, to be ready for powder coat on Monday.

We ran the pivot clamping mount pieces on the CNC, and finished all 32 of those, including the 4 with the 696 logo.

Other details from Sunday 2/9/14?

Here’s a couple pictures of the clamping pivot mounts:

IMG_20140209_184015 IMG_20140209_170523

Lab closing: 1:30 AM on 2/10/2014